I submitted a question at Area Committee last Tuesday asking for an update on the issues I raised in September and a date for our site visit. The response was as follows:
"Having consulted with colleagues in SDCC it is confirmed that no site visits are permissible on the construction site at present. This is a decision made in the context of Health and Safety on a large active construction site. There is no change to previously shared timelines and information shared at the last ACM remains current. The Chief Architect and his senior team are regularly on site and meet contractors to supervise project progress."
I am not happy with the lack of a site visit as there are ways and means to ensure it is done safely. It was also pointed out to me by a resident yesterday that there appear to be more workers on site at present. Other than that, all the information in the video and text below still applies:
Report from September
- Now Spring 2023, but only if we are lucky with sub-contractors -
- Site visit by Councillors to be looked at -
Dear all, I promised a few weeks back that I would provide more detail on the farcical delays with the refurbished leisure centre and pool project, At yesterday's Area Committee meeting, in reply to my motion and question, we got the most detailed breakdown yet of the outstanding works. The Council don't always answer queries fully, but they did provide some useful information all the same and also said they would look at my request for a site inspection by Councillors. As you will see below, the remaining works are largely in the hands of sub-contractors, but they are sizeable enough. Council management says that Q1 of next year is possible but only if the contractors can be sorted out satisfactorily. Many of you will be as cynical as I am about any projections given. At this stage even Council management are frustrated and embarrassed about the whole mess, but this doesn't make things go any faster. I again asked for an update on the management of the new complex and spaces being provided for former sports users, Esker Boxing Club and the Naรญonra. This response is provided further down. I also once more pointed out the issues caused by the car park being closed while construction is ongoing. While Council staff were quick to respond that this would not be a panacea for previously existing issues around school times, especially as the car park would be for centre users, having it open would certainly help. This is now going to drag on as a related issue. There's a lot of reading below I know, but it's important that people are aware of all the issues involved. As ever I will continue to keep this matter high on the agenda. Best wishes, Paul ----- MEETING OF LUCAN / PALMERSTOWN / NORTH CLONDALKIN AREA COMMITTEE Tuesday, September 27, 2022 MOTION NO. 17 MOTION: Councillor P. Gogarty ๐๐ก๐๐ญ ๐ญ๐ก๐ ๐๐ก๐ข๐๐ ๐๐ฑ๐๐๐ฎ๐ญ๐ข๐ฏ๐ ๐ฉ๐ซ๐จ๐ฏ๐ข๐๐๐ฌ ๐ ๐๐ฎ๐ซ๐ญ๐ก๐๐ซ ๐ฎ๐ฉ๐๐๐ญ๐ ๐จ๐ง ๐ญ๐ก๐ ๐ฆ๐ฎ๐๐ก-๐๐๐ฅ๐๐ฒ๐๐ ๐ซ๐๐๐ฎ๐ซ๐๐ข๐ฌ๐ก๐ฆ๐๐ง๐ญ ๐จ๐ ๐ญ๐ก๐ ๐ฅ๐๐ข๐ฌ๐ฎ๐ซ๐ ๐๐๐ง๐ญ๐ซ๐ ๐๐ง๐ ๐๐จ๐ง๐ฌ๐ญ๐ซ๐ฎ๐๐ญ๐ข๐จ๐ง ๐จ๐ ๐ญ๐ก๐ ๐ง๐๐ฐ ๐ฌ๐ฐ๐ข๐ฆ๐ฆ๐ข๐ง๐ ๐ฉ๐จ๐จ๐ฅ ๐ข๐ง ๐๐ฎ๐๐๐ง, ๐จ๐ฎ๐ญ๐ฅ๐ข๐ง๐ข๐ง๐ ๐ฐ๐ก๐๐ญ๐ก๐๐ซ ๐ ๐ซ๐๐ฏ๐ข๐ฌ๐๐ ๐๐ ๐๐๐๐ ๐จ๐ฉ๐๐ง๐ข๐ง๐ ๐ญ๐๐ซ๐ ๐๐ญ ๐๐๐ง ๐๐ ๐ฆ๐๐ญ; ๐จ๐ฎ๐ญ๐ฅ๐ข๐ง๐ข๐ง๐ ๐ฐ๐ก๐๐ญ ๐ฉ๐๐ง๐๐ฅ๐ญ๐ข๐๐ฌ, ๐ข๐ ๐๐ง๐ฒ ๐๐ซ๐ ๐๐๐ข๐ง๐ ๐ข๐ฆ๐ฉ๐จ๐ฌ๐๐ ๐๐จ๐ซ ๐ญ๐ก๐ ๐ฌ๐ข๐ ๐ง๐ข๐๐ข๐๐๐ง๐ญ ๐๐๐ฅ๐๐ฒ๐ฌ; ๐๐ง๐ ๐ฎ๐ง๐๐๐ซ๐ญ๐๐ค๐๐ฌ ๐ญ๐จ ๐๐ซ๐ซ๐๐ง๐ ๐ ๐ ๐ญ๐จ๐ฎ๐ซ ๐จ๐ ๐ญ๐ก๐ ๐๐จ๐ง๐ฌ๐ญ๐ซ๐ฎ๐๐ญ๐ข๐จ๐ง ๐ฌ๐ข๐ญ๐ ๐๐จ๐ซ ๐๐ฅ๐๐๐ญ๐๐ ๐ฆ๐๐ฆ๐๐๐ซ๐ฌ ๐ข๐ง ๐๐๐ซ๐ฅ๐ฒ ๐๐๐ญ๐จ๐๐๐ซ ๐ฌ๐จ ๐ญ๐ก๐๐ญ ๐ฐ๐ ๐๐๐ง ๐ ๐๐ญ ๐ ๐๐ฎ๐ฅ๐ฅ๐๐ซ ๐ฎ๐ง๐๐๐ซ๐ฌ๐ญ๐๐ง๐๐ข๐ง๐ ๐จ๐ ๐ญ๐ก๐ ๐ข๐ฌ๐ฌ๐ฎ๐๐ฌ ๐ข๐ง๐ฏ๐จ๐ฅ๐ฏ๐๐ ๐๐ง๐ ๐๐ ๐๐๐ฅ๐ ๐ญ๐จ ๐๐จ๐ฆ๐ฆ๐ฎ๐ง๐ข๐๐๐ญ๐ ๐ญ๐ก๐ข๐ฌ ๐๐๐ญ๐ญ๐๐ซ ๐ฐ๐ข๐ญ๐ก ๐ฎ๐ง๐๐๐ซ๐ฌ๐ญ๐๐ง๐๐๐๐ฅ๐ฒ ๐ข๐ซ๐๐ญ๐ ๐๐จ๐ง๐ฌ๐ญ๐ข๐ญ๐ฎ๐๐ง๐ญ๐ฌ. REPORT: Lucan Swimming Pool This โฌ13m+ project to deliver a new swimming pool in Lucan has been under construction since May 2019 but has been beset initially by Covid-related construction restrictions and further associated delays as well as subsequent challenges impacting the construction industry generally. Despite repeated assurances and commitments from the contractor, it is evident that the timeline for completion of the construction programme for Lucan Swimming Pool is significantly even behind the most recently revised completion date advised by the contractor, which was by the end of December 2022. The Council has had ongoing engagement and discussion with the contractor and the employerโs representative to achieve the earliest possible completion date as well as increasingly frequent site inspections to monitor progress and interrogate the resources and supply chain arrangements being applied to this contract by the contractor. In particular, there have been ongoing challenges with engagement of sub-contractors for works that are critical to the programme. As there are still significant works outstanding (see below) a completion date in Spring 2023 is the likely outcome if there is enhanced focus by the contractor together with their various sub-contractors and supply chain partners on optimising and effectively co-ordinating the remaining works. The majority of the outstanding items on the programme are to be carried out by sub-contractors and the contractor focus now is to try and get as many subcontractors working on-site as possible. Key remaining elements of the works programme include: Reglit glazing Standing seam roof Roof Lights Various mechanical and electrical services (which are critical to facilitating internally finishes, ceiling installation, painting etc.) Pool tank testing Pool hall ceiling finishes and tiling Snagging/commissioning Any potential site visits will need to be cleared by Architects and the SEO will investigate the potential for this in the coming weeks. ---- MEETING OF LUCAN / PALMERSTOWN / NORTH CLONDALKIN AREA COMMITTEE Tuesday, September 27, 2022 QUESTION NO. 11 QUESTION: Councillor P. Gogarty ๐๐จ ๐๐ฌ๐ค ๐ญ๐ก๐ ๐๐ก๐ข๐๐ ๐๐ฑ๐๐๐ฎ๐ญ๐ข๐ฏ๐ ๐๐จ๐ซ ๐๐ง ๐ฎ๐ฉ๐๐๐ญ๐ ๐จ๐ง ๐ญ๐ก๐ ๐๐ฉ๐ฉ๐จ๐ข๐ง๐ญ๐ฆ๐๐ง๐ญ ๐จ๐ ๐ ๐ฆ๐๐ง๐๐ ๐๐ฆ๐๐ง๐ญ ๐๐จ๐ฆ๐ฉ๐๐ง๐ฒ ๐๐จ๐ซ ๐ญ๐ก๐ ๐ซ๐๐๐ฎ๐ซ๐๐ข๐ฌ๐ก๐๐ ๐๐ฎ๐๐๐ง ๐๐๐ข๐ฌ๐ฎ๐ซ๐ ๐๐๐ง๐ญ๐ซ๐ ๐๐ง๐, ๐ ๐ข๐ฏ๐๐ง ๐ญ๐ก๐ ๐๐จ๐ง๐๐๐ซ๐ง๐ฌ ๐๐ฑ๐ฉ๐ซ๐๐ฌ๐ฌ๐๐ ๐๐ฒ ๐๐จ๐ซ๐ฆ๐๐ซ ๐ฎ๐ฌ๐๐ซ๐ฌ ๐๐ฌ ๐ฉ๐๐ซ ๐ฆ๐ฎ๐ฅ๐ญ๐ข๐ฉ๐ฅ๐ ๐ฆ๐จ๐ญ๐ข๐จ๐ง๐ฌ ๐๐ง๐ ๐ช๐ฎ๐๐ฌ๐ญ๐ข๐จ๐ง๐ฌ ๐จ๐ง ๐ญ๐ก๐ ๐๐ ๐๐ง๐๐, ๐ญ๐จ ๐จ๐ฎ๐ญ๐ฅ๐ข๐ง๐ ๐ข๐ง ๐ฅ๐ข๐ฌ๐ญ ๐๐จ๐ซ๐ฆ ๐ฐ๐ก๐ข๐๐ก ๐ข๐ ๐๐ง๐ฒ ๐จ๐ ๐ญ๐ก๐๐ฌ๐ ๐ก๐๐ฏ๐ ๐ซ๐๐๐๐ข๐ฏ๐๐ ๐ฐ๐ซ๐ข๐ญ๐ญ๐๐ง ๐๐จ๐ซ๐ซ๐๐ฌ๐ฉ๐จ๐ง๐๐๐ง๐๐ ๐จ๐ซ ๐ญ๐๐ฅ๐๐ฉ๐ก๐จ๐ง๐ ๐๐๐ฅ๐ฅ๐ฌ ๐๐ซ๐จ๐ฆ ๐๐จ๐ฎ๐ง๐๐ข๐ฅ ๐ฌ๐ญ๐๐๐ ๐ข๐ง ๐ญ๐ก๐ ๐ฅ๐๐ฌ๐ญ ๐ญ๐ก๐ซ๐๐ ๐ฆ๐จ๐ง๐ญ๐ก๐ฌ ๐ฎ๐ฉ๐๐๐ญ๐ข๐ง๐ ๐ญ๐ก๐๐ฆ ๐จ๐ง ๐ญ๐ก๐ ๐ฌ๐ข๐ญ๐ฎ๐๐ญ๐ข๐จ๐ง. REPLY: The process for the engagement of an operator to manage, operate and maintain the Lucan Leisure Campus, comprising the swimming pool and the existing leisure centre is at the final stage of a procurement process and it is expected that the successful candidate will be announced in October. It is envisaged that the successful operator will then be in a position to begin the required operational planning process. This will involve beginning an assessment process in relation to previous and future use plans. This will include a relevant partner engagement process.
Comments