top of page
Search

Lucan Pool Delay Update

Updated: Nov 8, 2022

I submitted a question at Area Committee last Tuesday asking for an update on the issues I raised in September and a date for our site visit. The response was as follows:


"Having consulted with colleagues in SDCC it is confirmed that no site visits are permissible on the construction site at present. This is a decision made in the context of Health and Safety on a large active construction site. There is no change to previously shared timelines and information shared at the last ACM remains current. The Chief Architect and his senior team are regularly on site and meet contractors to supervise project progress."


I am not happy with the lack of a site visit as there are ways and means to ensure it is done safely. It was also pointed out to me by a resident yesterday that there appear to be more workers on site at present. Other than that, all the information in the video and text below still applies:


Report from September


- Now Spring 2023, but only if we are lucky with sub-contractors -

- Site visit by Councillors to be looked at -


Dear all, I promised a few weeks back that I would provide more detail on the farcical delays with the refurbished leisure centre and pool project, At yesterday's Area Committee meeting, in reply to my motion and question, we got the most detailed breakdown yet of the outstanding works. The Council don't always answer queries fully, but they did provide some useful information all the same and also said they would look at my request for a site inspection by Councillors. As you will see below, the remaining works are largely in the hands of sub-contractors, but they are sizeable enough. Council management says that Q1 of next year is possible but only if the contractors can be sorted out satisfactorily. Many of you will be as cynical as I am about any projections given. At this stage even Council management are frustrated and embarrassed about the whole mess, but this doesn't make things go any faster. I again asked for an update on the management of the new complex and spaces being provided for former sports users, Esker Boxing Club and the Naรญonra. This response is provided further down. I also once more pointed out the issues caused by the car park being closed while construction is ongoing. While Council staff were quick to respond that this would not be a panacea for previously existing issues around school times, especially as the car park would be for centre users, having it open would certainly help. This is now going to drag on as a related issue. There's a lot of reading below I know, but it's important that people are aware of all the issues involved. As ever I will continue to keep this matter high on the agenda. Best wishes, Paul ----- MEETING OF LUCAN / PALMERSTOWN / NORTH CLONDALKIN AREA COMMITTEE Tuesday, September 27, 2022 MOTION NO. 17 MOTION: Councillor P. Gogarty ๐“๐ก๐š๐ญ ๐ญ๐ก๐ž ๐‚๐ก๐ข๐ž๐Ÿ ๐„๐ฑ๐ž๐œ๐ฎ๐ญ๐ข๐ฏ๐ž ๐ฉ๐ซ๐จ๐ฏ๐ข๐๐ž๐ฌ ๐š ๐Ÿ๐ฎ๐ซ๐ญ๐ก๐ž๐ซ ๐ฎ๐ฉ๐๐š๐ญ๐ž ๐จ๐ง ๐ญ๐ก๐ž ๐ฆ๐ฎ๐œ๐ก-๐๐ž๐ฅ๐š๐ฒ๐ž๐ ๐ซ๐ž๐Ÿ๐ฎ๐ซ๐›๐ข๐ฌ๐ก๐ฆ๐ž๐ง๐ญ ๐จ๐Ÿ ๐ญ๐ก๐ž ๐ฅ๐ž๐ข๐ฌ๐ฎ๐ซ๐ž ๐œ๐ž๐ง๐ญ๐ซ๐ž ๐š๐ง๐ ๐œ๐จ๐ง๐ฌ๐ญ๐ซ๐ฎ๐œ๐ญ๐ข๐จ๐ง ๐จ๐Ÿ ๐ญ๐ก๐ž ๐ง๐ž๐ฐ ๐ฌ๐ฐ๐ข๐ฆ๐ฆ๐ข๐ง๐  ๐ฉ๐จ๐จ๐ฅ ๐ข๐ง ๐‹๐ฎ๐œ๐š๐ง, ๐จ๐ฎ๐ญ๐ฅ๐ข๐ง๐ข๐ง๐  ๐ฐ๐ก๐ž๐ญ๐ก๐ž๐ซ ๐š ๐ซ๐ž๐ฏ๐ข๐ฌ๐ž๐ ๐๐Ÿ ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ‘ ๐จ๐ฉ๐ž๐ง๐ข๐ง๐  ๐ญ๐š๐ซ๐ ๐ž๐ญ ๐œ๐š๐ง ๐›๐ž ๐ฆ๐ž๐ญ; ๐จ๐ฎ๐ญ๐ฅ๐ข๐ง๐ข๐ง๐  ๐ฐ๐ก๐š๐ญ ๐ฉ๐ž๐ง๐š๐ฅ๐ญ๐ข๐ž๐ฌ, ๐ข๐Ÿ ๐š๐ง๐ฒ ๐š๐ซ๐ž ๐›๐ž๐ข๐ง๐  ๐ข๐ฆ๐ฉ๐จ๐ฌ๐ž๐ ๐Ÿ๐จ๐ซ ๐ญ๐ก๐ž ๐ฌ๐ข๐ ๐ง๐ข๐Ÿ๐ข๐œ๐š๐ง๐ญ ๐๐ž๐ฅ๐š๐ฒ๐ฌ; ๐š๐ง๐ ๐ฎ๐ง๐๐ž๐ซ๐ญ๐š๐ค๐ž๐ฌ ๐ญ๐จ ๐š๐ซ๐ซ๐š๐ง๐ ๐ž ๐š ๐ญ๐จ๐ฎ๐ซ ๐จ๐Ÿ ๐ญ๐ก๐ž ๐œ๐จ๐ง๐ฌ๐ญ๐ซ๐ฎ๐œ๐ญ๐ข๐จ๐ง ๐ฌ๐ข๐ญ๐ž ๐Ÿ๐จ๐ซ ๐ž๐ฅ๐ž๐œ๐ญ๐ž๐ ๐ฆ๐ž๐ฆ๐›๐ž๐ซ๐ฌ ๐ข๐ง ๐ž๐š๐ซ๐ฅ๐ฒ ๐Ž๐œ๐ญ๐จ๐›๐ž๐ซ ๐ฌ๐จ ๐ญ๐ก๐š๐ญ ๐ฐ๐ž ๐œ๐š๐ง ๐ ๐ž๐ญ ๐š ๐Ÿ๐ฎ๐ฅ๐ฅ๐ž๐ซ ๐ฎ๐ง๐๐ž๐ซ๐ฌ๐ญ๐š๐ง๐๐ข๐ง๐  ๐จ๐Ÿ ๐ญ๐ก๐ž ๐ข๐ฌ๐ฌ๐ฎ๐ž๐ฌ ๐ข๐ง๐ฏ๐จ๐ฅ๐ฏ๐ž๐ ๐š๐ง๐ ๐›๐ž ๐š๐›๐ฅ๐ž ๐ญ๐จ ๐œ๐จ๐ฆ๐ฆ๐ฎ๐ง๐ข๐œ๐š๐ญ๐ž ๐ญ๐ก๐ข๐ฌ ๐›๐ž๐ญ๐ญ๐ž๐ซ ๐ฐ๐ข๐ญ๐ก ๐ฎ๐ง๐๐ž๐ซ๐ฌ๐ญ๐š๐ง๐๐š๐›๐ฅ๐ฒ ๐ข๐ซ๐š๐ญ๐ž ๐œ๐จ๐ง๐ฌ๐ญ๐ข๐ญ๐ฎ๐ž๐ง๐ญ๐ฌ. REPORT: Lucan Swimming Pool This โ‚ฌ13m+ project to deliver a new swimming pool in Lucan has been under construction since May 2019 but has been beset initially by Covid-related construction restrictions and further associated delays as well as subsequent challenges impacting the construction industry generally. Despite repeated assurances and commitments from the contractor, it is evident that the timeline for completion of the construction programme for Lucan Swimming Pool is significantly even behind the most recently revised completion date advised by the contractor, which was by the end of December 2022. The Council has had ongoing engagement and discussion with the contractor and the employerโ€™s representative to achieve the earliest possible completion date as well as increasingly frequent site inspections to monitor progress and interrogate the resources and supply chain arrangements being applied to this contract by the contractor. In particular, there have been ongoing challenges with engagement of sub-contractors for works that are critical to the programme. As there are still significant works outstanding (see below) a completion date in Spring 2023 is the likely outcome if there is enhanced focus by the contractor together with their various sub-contractors and supply chain partners on optimising and effectively co-ordinating the remaining works. The majority of the outstanding items on the programme are to be carried out by sub-contractors and the contractor focus now is to try and get as many subcontractors working on-site as possible. Key remaining elements of the works programme include: Reglit glazing Standing seam roof Roof Lights Various mechanical and electrical services (which are critical to facilitating internally finishes, ceiling installation, painting etc.) Pool tank testing Pool hall ceiling finishes and tiling Snagging/commissioning Any potential site visits will need to be cleared by Architects and the SEO will investigate the potential for this in the coming weeks. ---- MEETING OF LUCAN / PALMERSTOWN / NORTH CLONDALKIN AREA COMMITTEE Tuesday, September 27, 2022 QUESTION NO. 11 QUESTION: Councillor P. Gogarty ๐“๐จ ๐š๐ฌ๐ค ๐ญ๐ก๐ž ๐‚๐ก๐ข๐ž๐Ÿ ๐„๐ฑ๐ž๐œ๐ฎ๐ญ๐ข๐ฏ๐ž ๐Ÿ๐จ๐ซ ๐š๐ง ๐ฎ๐ฉ๐๐š๐ญ๐ž ๐จ๐ง ๐ญ๐ก๐ž ๐š๐ฉ๐ฉ๐จ๐ข๐ง๐ญ๐ฆ๐ž๐ง๐ญ ๐จ๐Ÿ ๐š ๐ฆ๐š๐ง๐š๐ ๐ž๐ฆ๐ž๐ง๐ญ ๐œ๐จ๐ฆ๐ฉ๐š๐ง๐ฒ ๐Ÿ๐จ๐ซ ๐ญ๐ก๐ž ๐ซ๐ž๐Ÿ๐ฎ๐ซ๐›๐ข๐ฌ๐ก๐ž๐ ๐‹๐ฎ๐œ๐š๐ง ๐‹๐ž๐ข๐ฌ๐ฎ๐ซ๐ž ๐‚๐ž๐ง๐ญ๐ซ๐ž ๐š๐ง๐, ๐ ๐ข๐ฏ๐ž๐ง ๐ญ๐ก๐ž ๐œ๐จ๐ง๐œ๐ž๐ซ๐ง๐ฌ ๐ž๐ฑ๐ฉ๐ซ๐ž๐ฌ๐ฌ๐ž๐ ๐›๐ฒ ๐Ÿ๐จ๐ซ๐ฆ๐ž๐ซ ๐ฎ๐ฌ๐ž๐ซ๐ฌ ๐š๐ฌ ๐ฉ๐ž๐ซ ๐ฆ๐ฎ๐ฅ๐ญ๐ข๐ฉ๐ฅ๐ž ๐ฆ๐จ๐ญ๐ข๐จ๐ง๐ฌ ๐š๐ง๐ ๐ช๐ฎ๐ž๐ฌ๐ญ๐ข๐จ๐ง๐ฌ ๐จ๐ง ๐ญ๐ก๐ž ๐š๐ ๐ž๐ง๐๐š, ๐ญ๐จ ๐จ๐ฎ๐ญ๐ฅ๐ข๐ง๐ž ๐ข๐ง ๐ฅ๐ข๐ฌ๐ญ ๐Ÿ๐จ๐ซ๐ฆ ๐ฐ๐ก๐ข๐œ๐ก ๐ข๐Ÿ ๐š๐ง๐ฒ ๐จ๐Ÿ ๐ญ๐ก๐ž๐ฌ๐ž ๐ก๐š๐ฏ๐ž ๐ซ๐ž๐œ๐ž๐ข๐ฏ๐ž๐ ๐ฐ๐ซ๐ข๐ญ๐ญ๐ž๐ง ๐œ๐จ๐ซ๐ซ๐ž๐ฌ๐ฉ๐จ๐ง๐๐ž๐ง๐œ๐ž ๐จ๐ซ ๐ญ๐ž๐ฅ๐ž๐ฉ๐ก๐จ๐ง๐ž ๐œ๐š๐ฅ๐ฅ๐ฌ ๐Ÿ๐ซ๐จ๐ฆ ๐‚๐จ๐ฎ๐ง๐œ๐ข๐ฅ ๐ฌ๐ญ๐š๐Ÿ๐Ÿ ๐ข๐ง ๐ญ๐ก๐ž ๐ฅ๐š๐ฌ๐ญ ๐ญ๐ก๐ซ๐ž๐ž ๐ฆ๐จ๐ง๐ญ๐ก๐ฌ ๐ฎ๐ฉ๐๐š๐ญ๐ข๐ง๐  ๐ญ๐ก๐ž๐ฆ ๐จ๐ง ๐ญ๐ก๐ž ๐ฌ๐ข๐ญ๐ฎ๐š๐ญ๐ข๐จ๐ง. REPLY: The process for the engagement of an operator to manage, operate and maintain the Lucan Leisure Campus, comprising the swimming pool and the existing leisure centre is at the final stage of a procurement process and it is expected that the successful candidate will be announced in October. It is envisaged that the successful operator will then be in a position to begin the required operational planning process. This will involve beginning an assessment process in relation to previous and future use plans. This will include a relevant partner engagement process.

Comments


bottom of page